End of Trip Facility, 165 Walker Street

Who They Are

Address

165 Walker Street

Scope of project

Design and Construct

SQM

50 sqm

Cost of fitout

$155K

Timeline

6 Weeks

SCOPE OF WORKS

  • Design of new end of trip facility to allow for 4 new showers (one ambulant), 9 bike racks and 16 new lockers
  • Supply and install of new villa board partitions
  • Supply and install of new floor and wall tiles + waterproofing
    • Lulo Tile – Concrete look, matte finish tile
  • Readjustment of fire protection services to suit new layout
  • Specification, supply and install of all bathroom fixtures and fittings
    • Rocca Debba Wall Basins
    • Various Mizu Drift fittings
  • Supply and install of special joinery throughout
  • Supply and install of surface mounted 1000MM Bollards
  • Supply and install of 4 Bike Floor Parking Rack storage
  • Supply and install of four – door office gym shed lockers