50 Carrington End of Trip

Who They Are

Address

50 Carrington Street, Sydney

Scope of project

Construct

SQM

100 sqm

Cost of fitout

$320K

Timeline

6 weeks

SCOPE OF WORKS

  • Excavation of slab for all new hydraulic works
  • Installation of new mechanical ductwork and fire services
  • Install of all gyprock and laminate partitions
  • Custom joinery benches and lockers throughout
  • Supply and install of all new lighting, electrical and emergency points
  • Supply and install of tiled flooring and walls
  • Install of all FF&E to male and female bathrooms
  • Supply and install of all way finding from ground floor to basement Level 2
  • Supply and install of bollards and custom signage on the external facia