MCI

Who They Are

Address

19 Harris Street, Pyrmont NSW 2009

Scope of project

Design and Construction

SQM

462 sqm

Cost of fitout

$380K

Timeline

5 weeks

SCOPE OF WORKS

  • Design and creation of open plan workstation area / collaborative area, 4 meeting rooms and 2 boardrooms separated with an operable wall, kitchenette and reception area
  • Supply and install Signature verve carpet tiles to boardrooms
    • Signature Vivid Sky High to meeting room
    • Signature Grassy Knoll to meeting room
    • Signature Wild Violet to meeting room
    • Signature Carrot Cake to meeting room
    • Signature Wasabi pea to meeting room
    • Signature Vivid Lipstick to meeting room
  • Grinding to existing floor to create a polished concrete floor finish
  • Install of grid and tile ceiling to meeting and boardrooms
  • Strip out of existing grid and tile ceilings, spray concrete soffit and services a matte white finish
  • Supply and install CAT6 cabling and power throughout to service new layout
  • Modify fire protection services and mechanical services to suit new layout
  • Supply and install of 9Kw supplementary unit to boardroom
  • Supply and install of feature and pendant lights throughout
    • Laito matte black pendant
    • About Space Natural concrete Sunset pendants
    • About space Orange Accord pendants
  • Specification, supply and install of all workstations, chairs and breakout furniture
    • LIM diamond leg, black powdercoated workstations with fabric privacy screens
    • Executive L shape workstations with natural oak top finish
    • Modo collaboration banquettes
  • Design, supply and install of breakout kitchen in natural oak matte finish, benches and storage units
  • Supply and install of all 600MM frosted branding and reception signage
  • Supply and install of Black Schiavello garden feature wall